News

SF6 Phase-Out Moves Up the Voltage Ladder: The EU Deadlines Buyers Need to Know

Published: 2026-10-14 09:00:00 Views: 14

From Preference to Procurement Rule

For twenty years the argument against sulphur hexafluoride was environmental. With Regulation (EU) 2024/573, it became legal. The regulation, in force since February 2024 under the EU's F-gas framework, does not ban SF6 already in service — it prohibits placing new switchgear containing fluorinated greenhouse gases into operation, class by class, on fixed dates.

The Deadlines, Class by Class

Voltage classBan on putting new SF6 equipment into operation
Medium voltage, up to and including 24 kV1 January 2026
Medium voltage, above 24 kV up to 52 kV1 January 2030
High voltage, 52 kV to 145 kV (up to 50 kA)1 January 2028
Above 145 kV, or above 50 kA1 January 2032
Servicing with virgin SF6Prohibited from 1 January 2035 (reclaimed gas permitted, limited exceptions)

The upper end of the range is given the longest runway because replacing SF6 is hardest there: SF6 combines very high dielectric strength with strong arc-quenching ability, and an alternative gas must either be held at higher pressure or given more physical space to do the same job.

Why the First Deadline Matters Most

The 1 January 2026 date applies to up to and including 24 kV, which is precisely the bulk of the distribution upgrade cycle — the 12 kV and 24 kV indoor panels that utilities and industrial sites buy continuously. Any specification written after that date for a 12 kV panel has to be SF6-free, or the equipment cannot lawfully be put into operation in the EU.

Two clarifications that buyers routinely get wrong:

  • Existing equipment is not affected. The regulation does not require anyone to decommission working SF6 switchgear.
  • Component-level refurbishment is not "placing on the market". Replacing a single functional part inside an existing SF6 panel is treated differently from installing a whole new panel.

It Is Not Only Europe

  • United States: California has been phasing out new SF6 gas-insulated equipment by voltage and configuration since 2025, and New York adopted a comparable schedule with medium-voltage dates from 2027. Massachusetts takes a different route, requiring new GIS to demonstrate a very low annual leak rate rather than banning it outright.
  • United Kingdom: retains handling, leak-checking and certification controls, but has not adopted EU-style phase-out dates.
  • Elsewhere: reporting requirements and pilot deployments of SF6-free high voltage equipment are spreading, even where no ban exists.

What to Do With This

Whether or not a given project sits inside the EU, these dates are already shaping what manufacturers build and what utilities specify. A specification written in 2026 that still assumes SF6 as the default medium is a specification that will need rewriting. The practical move is to fix the insulation technology at the tender stage, confirm the relevant standard and type-test evidence, and then treat the gas medium as a locked requirement rather than a variable.

Inquiry